Diesel engine crusher Using Guidelines
Source:http://www.greatwallcrushers.c Author:GreatWallPosted:2015-05-25 Views:
Preparation work before starting
1. To check if there is enough lubricating grease in the bearings.
2 .To check if all the fasteners are completely tight.
3. To check if there is metal or some other nonbreakable sundries in the crusher.
4. To check the gap between hammers and cage bars.
5. Turn the rotor by hand , check to see if it runs in the right direction and if the hammer strikes other parts.
Starting
1. After checking, if all parts run normally , the machine can be started .
2. If there is unusual conditions after starting, workers should stop the machine at once and find out the problem , then restart the machine after eliminating the problem.
Operation and Maintenance
1. If the machine runs normally, then materials can be fed in.
2. Material should be fed in evenly and distributed evenly on the whole length of the rotor working part to avoid unbalance loading of rotor and increasing the loading of diesel engine.
3. To check the cage bars regularly, and clear the jam at once when it is blocked.
4. Under normal conditions, the temperature rises within 35℃, the highest temperature should not more than 70℃, the machine should be stopped at once if the temperature is higher than 70℃,then find out the problem and solve it.
5. First stop feeding materials when to stop the machine, turn off the diesel engine after all the materials in the crushing cavity are crushed.
6. To adjust the output size by the following ways:
(1)Change the type of the cage bar.
(2) Inset filler block in the groove of the cage bar frame to change the gap between the cage bars.
7. If the vibration increases suddenly, machine should be stopped at once, find out the problem and solve it.
8. When installing or changing the hammer , rotor should keep balance, the total weight of the five hammers on each hammer shaft should equals to that of the counter shaft, total deviation should not be more than 100 g (If it vibrate acutely during the trial run ,users can exchange the hammers on the single hammer shaft to maintain balance).
More information or problem, even about failure, troubleshooting and maintenance, pleasure CONTRACT US. It is a pleasure if I can help you.
Other relevant products:jaw crusher,cone crusher, Raymond mill, Roller crusher
1. To check if there is enough lubricating grease in the bearings.
2 .To check if all the fasteners are completely tight.
3. To check if there is metal or some other nonbreakable sundries in the crusher.
4. To check the gap between hammers and cage bars.
5. Turn the rotor by hand , check to see if it runs in the right direction and if the hammer strikes other parts.
Starting
1. After checking, if all parts run normally , the machine can be started .
2. If there is unusual conditions after starting, workers should stop the machine at once and find out the problem , then restart the machine after eliminating the problem.
Operation and Maintenance
1. If the machine runs normally, then materials can be fed in.
2. Material should be fed in evenly and distributed evenly on the whole length of the rotor working part to avoid unbalance loading of rotor and increasing the loading of diesel engine.
3. To check the cage bars regularly, and clear the jam at once when it is blocked.
4. Under normal conditions, the temperature rises within 35℃, the highest temperature should not more than 70℃, the machine should be stopped at once if the temperature is higher than 70℃,then find out the problem and solve it.
5. First stop feeding materials when to stop the machine, turn off the diesel engine after all the materials in the crushing cavity are crushed.
6. To adjust the output size by the following ways:
(1)Change the type of the cage bar.
(2) Inset filler block in the groove of the cage bar frame to change the gap between the cage bars.
7. If the vibration increases suddenly, machine should be stopped at once, find out the problem and solve it.
8. When installing or changing the hammer , rotor should keep balance, the total weight of the five hammers on each hammer shaft should equals to that of the counter shaft, total deviation should not be more than 100 g (If it vibrate acutely during the trial run ,users can exchange the hammers on the single hammer shaft to maintain balance).